Mauritania has commissioned the €122 million Boulenouar Wind Power Project. To help bring the project to fruition, ALE mobilized their specialist transport services to complete the transportation and installation of two electrical transformers, saving time and costs for a 100-MW wind farm project near Nouadhibou, Mauritania.
ALE’s experience in transportation across a range of sectors enabled them to eliminate a third from the operation’s schedule, which also saved costs. The abnormal load transport of the electrical transformers, weighing 95 tons each, crossed over 100 km. The route began at the Port of Nouadhibou and finished at a transformation center.
Once on site, the transformers were unloaded using heavy duty lifting equipment and discharged directly onto rails embedded in concrete. This enabled the transformers to then be rolled on their own wheels to their final position.
ALE was able to mobilize a team at short notice for the operation. For the specialist transport and installation, ALE utilized 6 axle lines of conventional trailer with a 250-ton capacity tractor, then 90-ton capacity hydraulic jacks for the unloading.
The new wind farm will be the second in Mauritania with more than three times as much potential power. It will consist of 39 wind turbines and construction is expected to finish in 2019.